Nama Chemicals Co. Announces Execution of two effluents wastewater treatment projects from calcium chloride plant and Epoxy Resin plant in Jubail Chemicals Company (JANA), subsidiary of Nama Chemicals Company.
Element List | Explanation |
---|---|
Project Start Date | 01/01/2023 |
Project Cost | 63 million Saudi riyals including Infrastructure and related civil work. |
Financing method for the project | Self-financing |
Expected completion date of the project | 30/06/2024 |
Expected Impact on the Company’s Financial Results | Annual reduction in operating cost by 27 million SAR approximately |
Expected Date on Which the Impact on the Financial Results of the Company will Start | 01/10/2024 |
Expected Date for the Pilot Production of the Project to Begin | 01/07/2024 |
Duration of the pilot production of the project | Tow months |
Expected date for the commercial production of the project | 01/09/2024 |
Executing Party/Counter Party in the Project/Contract | Green dimension environmental services Co. (Saudi Co.), and Confident Engineering International Co. (Gulf Co.)
For the engineering, procurements, and construction of treatment units for the effluent wastewater from calcium chloride plant and Epoxy Resin plant. |
Related Parties | None |