Al Yamamah Steel Industries Co. Announces an update on the latest development of Solar Project

Default Company 1304.O 0.00% 0.00 0.00

Element List Explanation
Date of previous announcement 2018-06-04 Corresponding to 1439-09-20
Progress % Phase I, 50% of the project
Expected completion date of the event Start up is expectd during Q1, 2019 and commercial operation is during Q2, 2019
Expenses related to the event and whether it changed or not with the justification No
Additional Information Financial impact is expected in quarter three of the the company cosolidated financial statement of the year ended 30/09/2019